| Stage |
Date |
| Mill Pond and the Northern Gateway East sites were acquired by Essential Land |
April 2010 |
| Planning application to prepare sites for redevelopment submitted |
August 2010 |
| Planning application to prepare sites for redevelopment determined |
Early September 2010 |
| Works commence to prepare sites for redevelopment |
Early October 2010 |
| Consultation on initial scheme commences |
Late October 2010 |
| Outline planning application for scheme submitted |
Late January 2011 |
| Outline planning application for scheme determined |
Early June 2011 |
| Planning application submitted for reserved matters (which may be separated into phases) |
Late 2011 |
| Planning application for reserved matters determined |
Early 2012 |
| Construction of scheme commences |
Mid 2012 |
| Completion of first phase |
2014 |
| Completion of scheme |
2018 |