Timetable

Stage Date
Mill Pond and the Northern Gateway East sites were acquired by Essential Land April 2010
Planning application to prepare sites for redevelopment submitted August 2010
Planning application to prepare sites for redevelopment determined Early September 2010
Works commence to prepare sites for redevelopment Early October 2010
Consultation on initial scheme commences Late October 2010
Outline planning application for scheme submitted Late January 2011
Outline planning application for scheme determined Early June 2011
Planning application submitted for reserved matters (which may be separated into phases) Late 2011
Planning application for reserved matters determined Early 2012
Construction of scheme commences Mid 2012
Completion of first phase 2014
Completion of scheme 2018